Illinois prompt payment for contractors: a short guide

Illinois builds payment deadlines, late interest and retainage caps into many private construction contracts. Here is who is in, who is out and the day counts.

Prepared by Prem Tax and Accounting Corp. Last checked against official sources on October 29, 2026.

The Illinois Contractor Prompt Payment Act (815 ILCS 603) writes payment deadlines, late interest and retainage limits into many private construction contracts. It names no enforcing agency. It matters to owners, contractors and subcontractors, like the other Illinois laws here. We check jobs with the Pay-App Stopwatch Review. The official text is on the Illinois General Assembly website.

The short version
  • Excluded: contracts that use public funds, single-family homes, and multi-family buildings with 12 or fewer units.
  • The owner has 15 calendar days from approving a payment application to pay.
  • Unless a written withholding statement is sent first, an application is deemed approved once 25 days pass from receipt.
  • Late payment carries 10% interest a year, and the contractor may suspend work after giving 7 calendar days' written notice.

Slide show: Five slides on the prompt payment rules

  1. What it is

    Payment terms built into private construction contracts.

  2. Who is out

    Public-funds jobs, single-family homes, multi-family buildings of up to 12 units.

  3. Owner's clock

    Pay within 15 days of approval. Without a written withholding statement, 25 days of silence counts as approval.

  4. Pass-down

    Contractors pay subcontractors within 15 days of receipt, for accepted work.

  5. Retainage

    At most 10% of a payment before the job is half done, then 5%.

Who it covers

GroupCovered?Note
Private contracts and subcontracts for work on Illinois real propertyYesNo size threshold.
Contracts requiring public fundsNoExcluded.
Single-family homes; multi-family buildings with no more than 12 unitsNoExcluded.

The numbers

ItemAmount or limitYear
Owner pays after approval15 calendar days, if the contractor performed2026
Deemed approval25 days after receipt, without a written withholding statement2026
Pay-down to subcontractorsDue 15 calendar days from receipt2026
Late interest10% per year2026
Notice before suspending7 calendar days, written2026
Retainage cap10% before 50% complete; 5% from 50% on2026
Days in the payment cycle, 2026 days
Approval deemed given25
Owner payment15
Subcontractor pay-down15
Notice to suspend7

Source: 815 ILCS 603/10 and 603/15

Public Act 104-168 (House Bill 1224), effective June 1, 2027, adds public works retainage limits through the Public Construction Bond Act, not this Act.

Our checklist

The Pay-App Stopwatch Review asks five questions about a covered job.

  • Start: what date did the payment application arrive?
  • Day 25: did a written statement go out first, giving the amount withheld and the reason?
  • Day 15: was payment made, and passed down, within 15 days?
  • Retainage: is no more than 10% held before halfway, and 5% after?
  • Stop: was 7 calendar days' written notice given before work was suspended?

Mistakes people make

  • Missing the day 25 deadline, so the application is deemed approved.
  • Treating a message to the architect or lender as approval. Under the Act, it is not approval.
  • Withholding everything for a small defect instead of the reasonable value of the faulty part.

Call an attorney about lien claims, suspension, retainage clauses or jobs mixing public and private money.

Common questions

What can a contractor do if the owner pays late?

Interest of 10% a year applies, and work may be suspended without breach after 7 calendar days' written notice. Lien rights come from the Mechanics Lien Act.

Is retainage capped at 10% for the whole job?

No. Before the job is half done, the cap is 10% of each payment. From 50% complete, no more than 5% may be held.

Does the Act cover home remodeling?

Usually not. The Act excludes work on single-family homes and on multi-family buildings with 12 or fewer units. Public-funds contracts are excluded too.

Official sources

Keep reading

Questions about how a law touches your payroll, taxes or entity? Keshav Agrawal is a U.S. CPA and a Chartered Accountant (CA) from India. We handle the tax and accounting side and can work alongside your attorney. We are not a law firm and cannot give legal advice. Book a 20-minute call or send us a message.

Let's talk about your taxes, your business, your plans.

Tell us what you need and we will get back to you quickly. There is no pressure: just a friendly conversation and a clear next step.

Prem Tax and Accounting Corp
4260 Westbrook Dr, Suite 107
Aurora, IL 60504
Phone number (shown as a picture)Monday to Friday, 9:00 am to 5:00 pm, by appointment. Saturday and Sunday by appointment when needed.

Prefer a call back? Leave your number.

CallBook a call